FACILITY CONDITION AUDIT - 20 UNIT HOUSING COMPLEX Client: Friendship Place D'Amitie, Chelmsford Project: Complete audit for 20 units covering all elements of the buildings.
FACILITY CONDITION AUDIT - 54 UNIT HOUSING COMPLEX Client: Shamrock Non-Profit Homes, Sudbury Project: Complete audit for 54 units covering all elements of the buildings.
FACILITY CONDITION AUDIT - 55 UNIT HOUSING COMPLEX Client: Maisons St. Jacques Housing Cooperative, Hanmer Project: Complete audit for 55 units covering all elements of the buildings. Also included was mould and indoor air quality testing.
CAMPUS WIDE FACILITY CONDITION AUDIT Client: Canadore College/Nipissing University, North Bay Project: Campus audit of the architectural, structural, mechanical and electrical equipment and systems using Internet based facility condition software and data base. Total area to be audited is approx. 780,000 ft2.
CAMPUS WIDE FACILITY CONDITION AUDIT Client: Cambrian College, Sudbury Project: Campus audit of the architectural, structural, mechanical and electrical equipment and systems using Internet based facility condition software and data base. Total area to be audited is approx. 750,000 ft2.
CAMPUS WIDE FACILITY CONDITION AUDIT Client: Laurentian University, Sudbury Project: Campus audit of the architectural, structural, mechanical and electrical equipment and systems using Internet based facility condition software and data base. Total area to be audited is approx. 1.2 million ft2.
OJIBWAY CLUB, POINT AU BARIL Client: Ojibway Club Project: Private lodge on an island in Georgian Bay. Audit consisted of reviewing all buildings from electrical point of view.
MANITOWANING BAY RESORT Client: Stefura, Nicholls, Yallowega Architects Project: Mechanical and electrical audit for a seasonal tourist resort up for sale.
WARREN COMMUNITY CENTRE Client: Township of Markstay-Warren Project: Facility audit covering architectural, structural, mechanical and electrical equipment and systems including cost estimates.
SUDBURY ALGOMA HOSPITAL Client: Network North - The Community Mental Health Group Project: Detailed indoor air quality investigation consisting of review of existing heating, ventilation and air conditioning systems, placement of C02 indoor air quality monitor in all areas of the building and interviews with staff.
BUILDING EVALUATION REPORT BAFFIN REGIONAL HOSPITAL, IQUALUIT, FROBISHER BAY Client: Cotnam Belair Deshaies Associate Architects Project: Facility condition audit for a hospital under the jurisdiction of Health & Welfare Canada Included were all mechanical and electrical equipment and systems.
MOOSE FACTORY HOSPITAL COMPLEX, MOOSE FACTORY Client: Cotnam Belair Associate Architects Inc., Timmins Project: Conduct a facility audit of the mechanical/electrical equipment and systems identifying shortcomings and recommendations for improvements. A major component of the audit was to identify areas where energy efficiency could be improved.
NORTHERN COLLEGE OF APPLIED ARTS & TECHNOLOGY, SOUTH PORCUPINE, KIRKLAND LK. & HAILEYBURY CAMPUSES Client: Cotnam Belair Associate Architects Inc., Timmins Project: Conduct a facility audit for three campuses and develop a life cycle program to replace mechanical/electrical equipment and systems with a particular emphasis on energy efficiency.
ENERGY MANAGEMENT - LIGHTING SYSTEM AUDITS, VARIOUS SCHOOLS, PHASE, I, II, III, IV Client: Sudbury District Roman Catholic Separate School Board Project: Conduct audit of existing lighting systems specifically from an energy usage point of view and quality of lighting.
|